Bridge work will restrict lanes on I-81 and I-83 near Harrisburg Monday and Tuesday
The John Harris Bridge gets deck patching overnight Monday
I-83 southbound at the John Harris Bridge, Harrisburg to Lemoyne
- 8 p.m. to 6 a.m.Deck patching leaves I-83 south with one lane
- Dates
- Mon., Nov. 16 to Tue., Nov. 17
- Stretch
- Exit 43 to Exit 42
Source: ABC27
View as table
| When | What |
|---|---|
| 8 p.m. to 6 a.m. | Deck patching leaves I-83 south with one lane |
| Dates | Mon., Nov. 16 to Tue., Nov. 17 |
| Stretch | Exit 43 to Exit 42 |
If you drive I-81 or I-83 around Harrisburg early this week, give yourself extra time. PennDOT announced bridge work that will bring lane restrictions on I-81 and at the John Harris Bridge on I-83. The schedule can change with the weather, and we suggest checking 511PA before you head out.
- Exit 67A: southbound bridge to Route 22/230 East (Cameron Street)
- Exit 67B: northbound bridge to Route 22/322 West (Lewistown/State College)
- I-83 south: one lane, Second Street ramp to Lemoyne ramp
The John Harris Memorial Bridge is also at the center of a $1.3 billion project to “modernize” I-83 south in the Harrisburg area. PennDOT received an apparent low bidder on Friday. If the bid materials are approved, the contractor will receive a contract and be cleared to begin construction, and drivers can expect traffic shifts, lane restrictions, road closures and detours.
Bridge inspections and patching come first, then a long build
- Nov. 13PennDOT received an apparent low bidder for the I-83 south project.
- Nov. 16Northbound I-81 inspections run from 9 a.m. to 2 p.m.
- Nov. 16Deck patching on the John Harris Bridge starts at 8 p.m.
- Nov. 17Southbound I-81 inspections run 9 a.m. to 2 p.m.; patching ends at 6 a.m.
- 2027Construction on the I-83 south project is expected to begin.
- 2039PennDOT expects construction on the I-83 south project to last through 2039.